During a workshop assessment, the reported condition is: A continuity check is needed on a protective conductor. Under what condition should the resistance measurement be made?

Answers
Awith the circuit safely de-energized and isolated from hazardous sources
Busing the meter's current range across the supply
Cwhile maximum load current is flowing
Dafter disconnecting the conductor from every bonding point without documentation